By BIN WANG, Chief Underwriting Officer, NIORD
A KEY issue affecting the offshore wind industry is a lack of contracting uniformity, which creates uncertainty for the parties to the contract, as well as for underwriters.
As an initial matter, the operator may wish to pursue either a multi-contracting or an EPCI strategy [1].
Take, for example, a hypothetical export cable work package. An operator pursuing a multi-contracting strategy will sign separate contracts with (1) an export cable manufacturer, and (2) a vessel-providing transportation and installation (T&I) contractor. The interface between these two contracts is managed by the operator, who would typically issue the cable procured from (1) as Free Issue Material (FIM) to (2).
If the operator decides to pursue an Engineering, Procurement, Construction, and Installation (EPCI) strategy, the shape of the EPCI contracting counterparty itself may vary. The options can be extensive:
a. the rare entity which is both (1) and (2);
b. (1) who then charters in a suitable vessel and crew for T&I;
c. (2) who then procures cable; or
d. a newly created JV or consortium entity comprised of (1) and (2). Here, whilst the operator has fewer contractual interface management concerns, additional contractual interfaces may arise within the EPCI contracting counterparty itself.
The complexity of these additional contractual interfaces (a contract for vessel charter in the case of (b), a procurement contract in the case of (c), or a JV/consortium agreement in the case of (d), accompanied by contracts between the JV/consortium with each of the individual members of the JV/consortium) can also often be less visible to the operator.
When these parties ((1) and (2) in the case of multi-contract, or (a)/(b)/(c)/(d) in the case of an EPCI contract) contract with the operator, there are also few pre-established norms. Whereas the offshore oil and gas industry has generally settled into a knock-for-knock regime, offshore wind contracting remains rooted in an onshore culture, with liabilities routinely allocated based upon a freedom of contract philosophy, and variances thereby arising due to commercial considerations. Two main aspects of this phenomenon of bespoke negotiations include the extent to which the operator’s contracting counterparty is given access to the Construction All Risks WINDCAR insurance policy (also known as an OCIP – an Owner Controlled Insurance Policy) procured by the operator, and the extent of the counterparty’s guarantees/warranties/defects liability obligations to the operator.
There can often be a mismatch between these two scopes. If the latter is larger than the former, the counterparty may well need to be in the market for a Difference in Conditions/Difference in Limits (DIC/DIL) insurance policy, the cost of which may also be bargained so that the operator foots the bill. If, however, the latter is smaller than the former, underwriters of OCIPs may think they are giving broader cover than they actually are (when the OCIP is worded broadly, but contractual curtailments to access are not readily visible to underwriters), and inflate pricing correspondingly.
When speaking about procurement of Wind Turbine Generators (WTGs), the contracting complexities continue. The WTG Original Equipment Manufacturer (OEM) will often sign both a Turbine Supply Agreement (TSA) and a Service and Maintenance Agreement (SMA) with the operator, both of which will contain various warranties and defects liability obligations. The bespoke nature of negotiations and contractual outcomes likewise persist in this space as well, in terms of both extent of WTG OEM access to the OCIP and extent of WTG OEM guarantees/warranties/defects liability obligations. In particular, as the European offshore wind WTG OEM space is now largely reduced to a duopoly,[2] shifts in contracting outcomes may begin to be observed. TSAs may now abridge the extent to which vessel hire costs are the responsibility of the WTG OEM, especially in certain geographic regions, when necessarily incurred due to provision of defective WTGs issues. SMAs may now also abridge the scope or number of services provided, particularly when dealing with a problematic WTG model with serial defect issues necessitating multiple and numerous Major Component Exchanges (MCEs).
For underwriters of OCIPs, all of this can be a nightmare of complexity and lack of transparency. Each OCIP WINDCAR Construction All Risks insurance policy becomes increasingly impossible to benchmark against each other as each contract/work package will have a unique outcome of extent of defects coverage afforded the EPCI or T&I Contractor (this could relate to attachment points, type and amount of sub-limit of various LEG coverages,[3] and type and duration of Maintenance & Discovery coverage)[4].
In respect of the TSAs and SMAs signed with WTG OEMs, because of the individual project-by-project nature of these negotiations, underwriters continue to have limited visibility into whether provision of vessel hire costs and/or extent to defects liability services provided have been limited in respect of any one particular risk, simply because there are constantly shifting contracting leverages, few contracting norms, and overall absolute freedom of contract in a duopoly environment.
When additional insured/co-assured status (and thereby the corresponding waivers of subrogation) and access to extended or guarantee maintenance provisions is granted by OCIP wordings in wide swaths to contractors/sub-contractors and manufacturers/suppliers “of all tiers,” details which relate to the chain of contracts with various sub-contractors (for example, the (a)/(b)/(c)/(d) arrangements described above in various EPCI arrangements) are more or less entirely opaque to OCIP underwriters trying to understand what benefits of the OCIP flow downward to which parties to what extent, and what warranty promises made by which contracting parties may flow upward to the potential benefit of OCIP underwriters.
At the end of the day, it is inevitable that insuring the construction of an offshore wind farm must necessarily take into account a significant number of various different contracts with various contracting counterparties. The industry would be better served if contracting were to become more uniform and consistent, which would also permit underwriters to better understand the risks to which they are exposed when writing these insurances. For example, as the International Federation of Consulting Engineers (FIDIC) realized that offshore wind contracting had been heavily utilizing their form contracts with substantial alterations on an ad hoc basis, work has begun to develop a new FIDIC contracting form specifically for the offshore wind industry.[5] The work done within The Nordic Association of Marine Insurers (CEFOR) in respect of the new Nordic Offshore Wind Insurance Conditions (NOWIC)[6] based on the Nordic Plan is another step in a similar direction based on the same goal: to improve uniformity, consistency, and predictability to the currently “Wild West” world of offshore wind contracting and insurance.
And whilst today’s arrangements can function, they are not ideal. Yes, contractors can procure DIC/DIL covers. Yes, grids have begun to appear in OCIPs, outlining to underwriters the relevant particulars of each main work package contracted for. But so long as OCIPs are meant to give operators broad umbrella cover for the entire project, a lack of contracting certainty will create inefficiencies. Underwriters might overcharge premiums for the appearances of cover which was always curtailed by contract. Or, when an operator principal assured has a broader scope of cover than a contractor additional insured/co-insured, a shrinking contractor’s guarantee/warranty/defects liability obligation scope to the operator in the contract not viewed by underwriters may leave underwriters with an unexpected claim via the operator principal assured.
Working together, the industry can do a better job of aligning contracting with insurance, and making contracting more predictable so that OCIP coverage is correspondingly more predictable, more cost-efficient, and less work-intensive to properly underwrite. Predictable interfaces logically will facilitate reduced interface risk. NIORD, with clients on both the operator’s side and the contractor’s side, looks forward to continued productive problem-solving relationships with both sides. When operators and contractors work together, and insurers such as NIORD provide best-in-class insurance products and services to both, the entire industry wins.
References
[1] https://guidetoanoffshorewindfarm.com/procurement-structures/
[3] https://nardac.com/when-is-covered-defective-workmanship-not-excluded-defective-workmanship/
[4] https://nardac.com/are-you-covered-maintenance-in-construction-insurance/
[5] https://fidic.org/node/41494
[6] https://cefor.no/clauses/nordic-offshore-wind-insurance-conditions/